The SAM lifecycle
Mode: reference.
An investment under SAM (the Softwired ATL Method) moves through six stages grouped into three acts. The stages are surfaced by Tollgate; the acts are the sponsor-facing framing.
| Act | Stages | The sponsor’s question |
|---|---|---|
| Commit | Discovery, Approval | Is this worth funding? |
| Run | Initiation, Delivery | Is it still worth it? |
| Evaluate | Close-out, Benefits Realisation | What did we get, and what next time? |
Charter approval states
Section titled “Charter approval states”Most stages are expressed as the investment thesis / business case’s approval
status (VALID_CHARTER_APPROVAL_STATUSES). The full ordered enum:
| State | Stage | Meaning |
|---|---|---|
Exploring |
Discovery | Candidate under pressure-test; relaxed gates. |
Draft |
Approval | Being prepared for submission (also where a returned case lands). |
Submitted |
Approval | Submitted for sponsor decision; ages visibly. |
Approved |
Approval → Run | Chartered. The investment is committed and runs. |
ClosingSubmitted |
Close-out | Close-out submission awaiting sponsor sign-off. |
Closed |
Close-out | Sponsor signed off; retired from active steering. Terminal (escape valve: reopenClosure). |
Archived |
Discovery / Approval | Killed with dignity — explored, not pursued. Terminal, findable. |
InRealisation |
Benefits Realisation | Benefits realisation under way. |
Realised |
Benefits Realisation | Sponsor verdict: benefits realised. Terminal. |
NotRealised |
Benefits Realisation | Sponsor verdict: benefits not realised. Terminal; carries an elevated lessons-learned field. |
InMaintenance |
Benefits Realisation | Realised investment graduated to annual review. |
Stage transitions
Section titled “Stage transitions”Discovery
Section titled “Discovery”Exploring→Submitted— PM submits the business case for approval.Exploring→Archived— killed with dignity (a one-line rationale). Terminal, but findable.
Approval
Section titled “Approval”Submitted→Approved— sponsor approves (optional rationale).Submitted→Draft— sponsor returns with structured notes (audit actioncharter.returned;returnNotescarry a severity and a pinned charter section).Submitted→Archived— sponsor archives rather than returns.
The single deliberate hard gate is the BCM / Adoption quartet on business case submission. Every other gate is a soft signal.
Return-note classification
Section titled “Return-note classification”Returned-case notes are classified by the sponsor:
| Field | Values |
|---|---|
Severity (VALID_RETURN_NOTE_SEVERITIES) |
Blocker, Significant, Minor |
Pinned section (VALID_RETURN_NOTE_SECTIONS) |
businessProblem, outcome, returnExpected, adoption, sponsor, steeringCommittee, theme, general |
Submitted-case aging
Section titled “Submitted-case aging”Submitted theses age against the site’s monthly steerco cadence
(APPROVAL_AGING_THRESHOLDS): amber at 7 days, red at 14, deep-red at 28. The
signal appears on surfaces the sponsor already opens; nothing is emailed.
Initiation (computed)
Section titled “Initiation (computed)”The morning-after-approval stage. A visible-but-non-blocking checklist composes
itself deterministically from the registers (INITIATION_CHECKLIST_ITEMS):
| Item ID | Satisfied when |
|---|---|
define-work-packages |
≥ 3 coarse work packages (INITIATION_MIN_WP_COUNT). |
name-owners |
every work package has an owner. |
set-baselines |
every work package has both budget and planned-date baselines locked. |
create-adoption-wp |
at least one work package of type “Adoption / Change”. |
schedule-first-steerco |
charter.firstSteercoScheduledFor is set. |
seed-rio-register |
≥ 3 R/I/O items (INITIATION_MIN_RIO_COUNT). |
The newly-approved window is 14 days (INITIATION_NEWLY_APPROVED_WINDOW_DAYS);
the checklist recedes when the first steerco is held or the window passes with
explicit acknowledgement (initiationDismissals). Checklist items are
recommendations, not stipulations.
Delivery (computed)
Section titled “Delivery (computed)”The long stretch while the investment runs (Approved, in flight). RAG plus
self-reported Outcome and Adoption confidence are kept current; materialised
risks route to decisions; the since-last-steerco ribbon answers “what’s changed?”
Close-out
Section titled “Close-out”Approved→ClosingSubmitted— PM submits the close-out record (as-built outcome + return, residual R/I/O dispositions, lessons, BAU handover).ClosingSubmitted→Closed— sponsor signs off. Terminal.Closed→ (reopenClosure) — escape valve to reopen.
Dispositions captured at close-out:
| Set | Values |
|---|---|
R/I/O disposition (VALID_RIO_DISPOSITIONS) |
Closed, TransferredToBau, Accepted, Pursued, Dropped |
Pending decision/change disposition (VALID_PENDING_DISPOSITIONS) |
Adjudicated, Withdrawn, ApprovedAsShipped, DeferredToBau |
Per-work-package scope disposition (VALID_SCOPE_DISPOSITIONS) |
DeliveredAsChartered, DeliveredReduced, DeliveredExpanded, Dropped, Deferred |
BAU handover state (VALID_BAU_HANDOVER_STATES) |
Pending, Acknowledged, Escalated |
Benefits Realisation
Section titled “Benefits Realisation”Lifecycle: Closed → InRealisation → Realised | NotRealised →
InMaintenance (or terminal).
- 90-day adoption checkpoint, a 6-month prose sniff-check, and a 12-month verdict.
- At the verdict the sponsor declares
Realised,NotRealised, or “not ready yet”. The declaration is the governance act; the said/got prose-pair is the artefact. No calculation.
BR review cadence (VALID_BR_CADENCE) is Monthly, Quarterly, or Annual;
default Quarterly (DEFAULT_BR_CADENCE). In-window reviews age against
BR_REVIEW_AGING_THRESHOLDS (amber 30 days, red 60, deep-red 120).